STANDARD OPERATING PROCEDURE – VFD PANEL PPM ACTIVITY
OBJECTIVE:
To establish a procedure for VFD Panel PPM activity.
POLICY:
Proactively identify, correct, and report VFD system defects and damages to reduce down time and risk of failures in the system.
RESPONSIBILITY:
Shift Engineer
PROCEDURE:
· Before activity all PPE’s should available.
· Apply LOTO equipment to the supply source.
· Make sure System is isolated from the main supply.
Cleaning the unit
· The filters should be cleaned or replaced if required. This includes the filters for general ventilation, and filters in storage cases for the VFDs.
· Vacuum the vents and storage space, and clean or replace the filters if required. (VFDs should not be cleaned with any solvents or water-based cleaning tools.)
Inspecting the parts.
· Tighten the connections and terminal blocks.
· Make sure the panel gaskets are in good condition, replace if required.
· Check the power supplies.
· At any job motto should be safety first.
· In case of any major problem, inform the Facility Manager immediately.
REVISION GUIDE:
Any change in the systems will need a change in the SOP.