STANDARD OPERATING PROCEDURE – SCRUBBER UNIT PPM ACTIVITY

 OBJECTIVE:

To establish a procedure for Scrubber Unit PPM activity.

 

POLICY:

Proactively identify, correct, and report Scrubber system defects and damages to reduce down time and improve life of the equipment.

 

RESPONSIBILITY:

 

Shift Engineer

 

PROCEDURE:

 

·        Before activity all PPE’s should available.

·        Apply LOTO equipment to the supply source.

·        Make sure System is isolated from the main supply.

·        Check/clean fan assembly

·        Lube fan bearings

·        Lube motor bearings

·        Check belts & sheaves – adjust as applicable

·        Tighten all nuts/bolts/mounting hardware

·        Check motor mounts and vibration pads

·        Check motor volts/amps

·        Inspect and tighten all electrical connections

·        Check fan operation

·        Check structural integrity of assembly

·        At any job motto should be safety first.

·        In case of any major problem, inform the Facility Manager immediately.


REVISION GUIDE:

Any change in the systems will need a change in the SOP.